Processing Dates and Rush Options
Delaware Division of Corporations
Processing Dates as of April 17, 2025
CORPORATIONS / BUSINESS ENTITIES
Documents are filed as of Delivery Date, Evidence issued as of Processing Date
Processing Basis | Rush Fee | State Cutoff | Processing Date |
1-Hour | $1,000 | 7:00 pm | April 17 |
2-Hour | $500 | 7:00 pm | April 17 |
Same Day | $100 – 200 | 2:00 pm | April 17 |
Next Day | $50 – 100 | 7:00 pm | April 16 |
Must Approval | $50 | 2:00 pm | April 16 |
Regular Approval | $0 | 11:59 pm | April 16 |
Routine | $0 | 11:59 pm | March 13 |
UCC’s
The current UCC through date is April 9, 2024
Processing Basis | Rush Fee | State Cutoff | Processing Date |
Next Day | $100 | 7:00 pm | April 16 |
Must Approval | $50 | 2:00 pm | April 16 |
Regular Approval | $0 | 11:59 pm | April 10 |
Routine | $0 | 11:59 pm | April 16 |